Phase 5D – Summary and Plans
Phase 5D
- Options – Favoured proposal. Single building totalling 8,080sqft (net).
- Suites - 6, ranging from 775 sqft to 1,875 sqft
- Parking - 1 space per 250 sqft
- Status - Planning Application yet to be submitted.
- Timescale - Planning Application, c. 3 to 4 months
- - Construction – 12 to 15 months
Specification – to be determined in conjunction with a prospective occupier.
- Specification – to be determined in conjunction with a prospective occupier.
- - BREEAM Excellent and an EPC A rating to be targeted.
| 5D Floor Areas | Individual Suites | Total Floor sq.ft. | Total M2 | Parking |
|---|---|---|---|---|
| Ground Floor | 2 x 1,370 sq.ft. | 2,740 | 255 | 11 |
| First Floor | 2 x 1,875sq.ft. | 3,750 | 349 | 15 |
| Second Floor | 815sq.ft. and 775sq.ft. | 1,590 | 148 | 6 |
| Totals | 8,080 | 752 | 32 |